The Kultuma construction site started on 11th month of 2023 and the completion date is planned to be at the end of 2024.
In Kultuma, we are planning to complete the installation of 4 mills, conveyors, pumps, ceiling cranes, hydrocyclones, tanks and package equipment in the mill area, as well as all the steel in that area, and complete them with commissioning and testing.
We are responsible of the grinding unit that includes the installation of;
- 2 SAG mills (9150 diameter) and 2 ball mills (6150 diameter),
- 4 cone crushers with the capacity of 110 t/h (each one),
- steel structure of whole grinding unit that including platforms and structure under the equipment,
- screens,
- hydrocyclone,
- concentrators,
- whole transfer conveyors,
- whole non-standard equipment.
PROJECT DETAILS
Location: Zabaykalsky Krai, Russia
Type of Contract: Subcontractor of East Contech
Equipment: Ersel, Sever Mineral, Metso, Heinan Heavy Industry
Period of Contract: 2023 – 2025
Activities: Installation of grinding unit and all the parts related to it