The fabrication and installation works of process pipelines at the Amur-Agro site commenced on January 25, 2026, and are currently ongoing. The planned completion date is August 2026.
Damar Heavy Industries is carrying out the fabrication and installation works of a total of 45,000 WDI NV outdoor pipelines and 20,000 meters of process pipelines within the scope of the project. Currently, 10% of the pipeline installation works have been completed, and activities are continuing as planned.
At the Amur-Agro site, the construction of one of the largest industrial vegetable oil production facilities in the region, where soybeans and rapeseed will be processed, is ongoing.